Difference between revisions of "Calligra/Schedules/2.9/Release Plan"

Jump to: navigation, search
Line 37: Line 37:
 
== 2.9.3 ==
 
== 2.9.3 ==
 
* Tagging April 25th
 
* Tagging April 25th
* Release 29th
+
* Release April 29th -- Cancelled (even if it can be available for download in some distros)
  
 
== 2.9.4 ==
 
== 2.9.4 ==
* Tagging May 23rd
+
* Tagging May 2nd
* Release 27th
+
* Release May 6th
 +
 
 +
== 2.9.5 ==
 +
* Tagging May 30th
 +
* Release June 3rd
 +
 
 +
Subsequent release will be planned on a case-by-case basis.
  
 
Subsequent release will be planned on a case-by-case basis.
 
Subsequent release will be planned on a case-by-case basis.

Revision as of 21:02, 29 April 2015

See also: Feature Plan, Quality Control

Note-box-icon.png
Note
Status: unreleased

Freezes

Master is never frozen for features or strings. The branch calligra/2.9 is always frozen for features or strings.

Testing

Beta 1 (2.8.90)

  • Tagging and branching (calligra/2.9) December 6th (no big merge on that day)
  • Release December 10th

Beta 2 (2.8.91)

  • Tagging January 11th
  • Release January 15th

Beta 3 (2.8.92)

  • Tagging February 8th
  • Release February 12th

Stable releases

2.9.0

  • Tagging February 22nd
  • Release February 26th

2.9.1

  • Tagging March 7th
  • Release March 11th

2.9.2

  • Tagging March 28th
  • Release April 1st

2.9.3

  • Tagging April 25th
  • Release April 29th -- Cancelled (even if it can be available for download in some distros)

2.9.4

  • Tagging May 2nd
  • Release May 6th

2.9.5

  • Tagging May 30th
  • Release June 3rd

Subsequent release will be planned on a case-by-case basis.

Subsequent release will be planned on a case-by-case basis.