Calligra/Schedules/2.9/Release Plan
See also: Feature Plan, Quality Control
Freezes
Master is never frozen for features or strings. The branch calligra/2.9 is always frozen for features or strings.
Testing
Beta 1 (2.8.90)
- Tagging and branching (calligra/2.9) December 6th (no big merge on that day)
- Release December 10th
Beta 2 (2.8.91)
- Tagging January 11th
- Release January 15th
Beta 3 (2.8.92)
- Tagging February 8th
- Release February 12th
Stable releases
2.9.0
- Tagging February 22nd
- Release February 26th
2.9.1
- Tagging March 7th
- Release March 11th
2.9.2
- Tagging March 28th
- Release April 1st
2.9.3
- Tagging April 25th
- Release April 29th -- Cancelled (even if it can be available for download in some distros)
2.9.4
- Tagging May 2nd
- Release May 6th
2.9.5
- Tagging May 30th
- Release June 3rd
2.9.6
- Tagging July 4th
- Release July 8th
2.9.7
(delayed 1 month because of regressions)
- Tagging August 29th
- Release September 2nd
2.9.8
- Tagging Sat, October 3rd
- Release Wed, October 7th
2.9.9
- Tagging Sat, October 31st
- Release Wed, November 4th
2.9.10
- Tagging Sat, November 28th
- Release Wed, December 2nd
2.9.11
- Tagging Sat, Jan 30th
- Release Wed, Feb 3rd
2.9.12
- Tagging Sat, Mar 5th
- Release Wed, Mar 9th
Subsequent release will be planned on a case-by-case basis.