Scrum meeting of the 2010-10-11
Work done since the last Scrum meeting
- Finished the powerpoint presentation
- Chatted with Guillaume on IRC
- Planned the 1st sprint
- Validated user stories
- Got back and modified the kde-silk project from Gitorious
- Talked about scrum meetings planning
Issues encountered
- IceScrum bugs
- Trouble with internet connections
Work to do until the next Scrum meeting
- Define a prelimilary architecture of the library
- Chat with “sebas” on IRC
- Contact “ervin” about the tests
- Update the project vision
- Make the definition of done