Scrum meeting of 2010-11-11
Work done since the last Scrum meeting
- Finish Mockup and send it to the product owner
- Make a minimalist widget
- Begin a minimalist dataengine
- Architecture document diagram
- Finish login tests
- Usergroup update class and tests
Encountered difficulties
- Slot comportment
- Do Scrum Meeting a holiday
Work to do until the next Scrum meeting
- Begin Logout class and tests
- Finish Mockup according to the product owner
- Talk about L3 presentation