Freezes

Master is never frozen for features or strings. The branch calligra/2.5 is always frozen for features or strings.

Testing

Alpha (2.4.90)

  • Tagging May 25th (no big merge on that day)
  • Release May 30th

Beta (2.4.91)

  • Tagging and branching (calligra/2.5) June 15th (no big merge on that day)
  • Release June 20th

RC (2.4.92)

  • Tagging July 6th (no big merge on that day)
  • Release July 11th

Stable releases

The final release should happen within three weeks after the RC.