Calligra/Schedules/2.6/Release Plan
See also: Feature Plan, Quality Control
Freezes
Master is never frozen for features or strings. The branch calligra/2.6 is always frozen for features or strings.
Testing
Alpha (2.5.90)
- Tagging October 5th (no big merge on that day)
- Release October 10th
Beta (2.5.91)
- Tagging and branching (calligra/2.6) October 26th (no big merge on that day)
- Release October 31th
RC (2.5.92)
- Tagging November 24th (no big merge on that day)
- Release November 28th
RC2 (2.5.93)
Was sometime in december
RC3 (2.5.94)
- Tagging 12th December
- Release 15th December
Stable releases
2.6.0
- Tagging 2nd February
- Release 5th February
The first stable release should happen about three weeks after the RC, if everything is in order.