All deadlines are due 23:59 UTC, but if you need a few more hours, notify someone from the release team. | All deadlines are due 23:59 UTC, but if you need a few more hours, notify someone from the release team. | ||
You can also add [https://phabricator.kde.org/calendar/export/ics/ | You can also add [https://phabricator.kde.org/calendar/export/ics/g4bud5r6cnbklugkqvlw/events_release.ics phabricator's calendar events_release.ics] as remote calendar to korganizer so you always have the release schedule near you. | ||
=== Thursday, July 12, 2018: KDE Applications 18.08 Dependency Freeze === | === Thursday, July 12, 2018: KDE Applications 18.08 Dependency Freeze === |
Revision as of 01:39, 10 July 2018
All deadlines are due 23:59 UTC, but if you need a few more hours, notify someone from the release team.
You can also add phabricator's calendar events_release.ics as remote calendar to korganizer so you always have the release schedule near you.
Thursday, July 12, 2018: KDE Applications 18.08 Dependency Freeze
From this moment on it is not allowed to add new dependencies or bump dependencies versions. It is possible to get an exception for this. Post the patch to reviewboard and add the release-team as reviewer. We will check if the dependency is needed and is available on all platforms.
In other words: If you have a feature that requires a new dependency or a version of a dependency that is higher than currently checked for in the build system, you need to have committed this change before this date.
Thursday, July 19, 2018: KDE Applications 18.08 Freeze and Beta (18.07.80) tag & release
Only bugfixes from this point on. Bugfixes needing user visible text changes need approval from [email protected]
Beta is tagged (tag name is v18.07.80). As soon as the tarballs have been confirmed to build and the Release Team thinks they meet enough quality it will be released
Thursday, August 2, 2018: KDE Applications 18.08 RC (18.07.90) Tagging and Release
Release Candidate is tagged (tag name is v18.07.90). As soon as the tarballs have been confirmed to build and the Release Team thinks they meet enough quality it will be released
Thursday, August 9, 2018: KDE Applications 18.08 Tagging
The branch is frozen for final release tagging (tag name is v18.08.0). Only urgent fixes, such as those fixing compilation errors, should be committed.
Thursday, August 16, 2018: KDE Applications 18.08 Release
Final release is released for general consumption.
Monday, September 3, 2018: KDE Applications 18.08.1 tagging
Minor release is tagged and made available to the packagers.
Thursday, September 6 2018: KDE Applications 18.08.1 release
Minor release is released to the public.
Monday, October 8, 2018: KDE Applications 18.08.2 tagging
Minor release is tagged and made available to the packagers.
Thursday, October 11, 2018: KDE Applications 18.08.2 release
Minor release is released to the public.
Monday November 5, 2018: KDE Applications 18.08.3 tagging
Minor release is tagged and made available to the packagers.
Thursday, November 8, 2018: KDE Applications 18.08.3 release
Minor release is released to the public.