Calligra/Schedules/2.6/Release Plan: Difference between revisions

From KDE Community Wiki
No edit summary
Line 35: Line 35:
* Release 5th February
* Release 5th February


The first stable release should happen about three weeks after the RC, if everything is in order.
== 2.6.1 ==
* Tagging 16th February
* Release 19th February
 
== 2.6.2 ==
* Tagging 9th March
* Release 13th March
 
== 2.6.3 ==
* Tagging 6th April
* Release 10th April
 
== 2.6.4 ==
* Tagging 4th May
* Release 8th May

Revision as of 10:27, 23 January 2013

See also: Feature Plan, Quality Control

Note

Status: in development, Alpha

Freezes

Master is never frozen for features or strings. The branch calligra/2.6 is always frozen for features or strings.

Testing

Alpha (2.5.90)

  • Tagging October 5th (no big merge on that day)
  • Release October 10th

Beta (2.5.91)

  • Tagging and branching (calligra/2.6) October 26th (no big merge on that day)
  • Release October 31th

RC (2.5.92)

  • Tagging November 24th (no big merge on that day)
  • Release November 28th

RC2 (2.5.93)

Was sometime in december

RC3 (2.5.94)

  • Tagging 12th December
  • Release 15th December

Stable releases

2.6.0

  • Tagging 2nd February
  • Release 5th February

2.6.1

  • Tagging 16th February
  • Release 19th February

2.6.2

  • Tagging 9th March
  • Release 13th March

2.6.3

  • Tagging 6th April
  • Release 10th April

2.6.4

  • Tagging 4th May
  • Release 8th May