Calligra/Schedules/2.6/Release Plan: Difference between revisions

From KDE Community Wiki
No edit summary
No edit summary
Line 20: Line 20:
* Tagging November 24th (no big merge on that day)
* Tagging November 24th (no big merge on that day)
* Release November 28th
* Release November 28th
== RC2 (2.5.93) ==
Was sometime in december
== RC3 (2.5.94) ==
* Tagging 12th December
* Release 15th December


= Stable releases =
= Stable releases =
== 2.6.0 ==
* Tagging 2nd February
* Release 5th February


The first stable release should happen about three weeks after the RC, if everything is in order.
The first stable release should happen about three weeks after the RC, if everything is in order.

Revision as of 10:25, 23 January 2013

See also: Feature Plan, Quality Control

Note

Status: in development, Alpha

Freezes

Master is never frozen for features or strings. The branch calligra/2.6 is always frozen for features or strings.

Testing

Alpha (2.5.90)

  • Tagging October 5th (no big merge on that day)
  • Release October 10th

Beta (2.5.91)

  • Tagging and branching (calligra/2.6) October 26th (no big merge on that day)
  • Release October 31th

RC (2.5.92)

  • Tagging November 24th (no big merge on that day)
  • Release November 28th

RC2 (2.5.93)

Was sometime in december

RC3 (2.5.94)

  • Tagging 12th December
  • Release 15th December

Stable releases

2.6.0

  • Tagging 2nd February
  • Release 5th February

The first stable release should happen about three weeks after the RC, if everything is in order.