Revision as of 08:57, 21 April 2012
Freezes
Master is never frozen for features or strings. The branch calligra/2.5 is always frozen for features or strings.
Testing
Alpha (2.3.90)
- Tagging May 25th (no big merge on that day)
- Release May 30th
Beta (2.3.91)
- Tagging and branching (calligra/2.5) June 15th (no big merge on that day)
- Release June 20th
RC (2.3.92)
- Tagging July 6th (no big merge on that day)
- Release July 11th
Stable releases
The final release should happen within three weeks after the RC.