Calligra/Schedules/2.8/Release Plan: Difference between revisions
No edit summary |
(→2.8.4) |
||
Line 40: | Line 40: | ||
== 2.8.4 == | == 2.8.4 == | ||
* Tagging June 14th | '''Postponed because of found regressions [http://lists.kde.org/?l=calligra-devel&m=140386344927957&w=2]; 2.8.5 planned shortly instead.''' | ||
* Release June 18th | * <strike>Tagging June 14th</strike> | ||
* <strike>Release June 18th</strike> | |||
== 2.8.5 == | |||
This release replaces 2.8.4 | |||
* Tagging June/July ?? | |||
* Release June/July ?? | |||
== 2.8.6 == | |||
* Tagging early August | |||
* Release early August |
Revision as of 22:04, 29 June 2014
See also: Feature Plan, Quality Control
Freezes
Master is never frozen for features or strings. The branch calligra/2.8 is always frozen for features or strings.
Testing
Beta 1 (2.7.90)
- Tagging and branching (calligra/2.8) November 30th (no big merge on that day)
- Release December 3rd
Beta 2 (2.7.91)
- Tagging January 11th (no big merge on that day)
- Release January 15th
Beta 3 (2.7.92)
- Tagging February 9th
- Release February 12th
Stable releases
2.8.0
- Tagging March 2
- Release March 5
2.8.1
- Tagging March 24th
- Release March 28th
2.8.2
- Tagging April 12th
- Release April 16th
2.8.3
- Tagging May 10th
- Release May 14th
2.8.4
Postponed because of found regressions [1]; 2.8.5 planned shortly instead.
Tagging June 14thRelease June 18th
2.8.5
This release replaces 2.8.4
- Tagging June/July ??
- Release June/July ??
2.8.6
- Tagging early August
- Release early August