Calligra/Schedules/2.5/Release Plan: Difference between revisions

From KDE Community Wiki
Line 11: Line 11:
* Release May 30th
* Release May 30th


== Beta (2.3.91) ==
== Beta (2.4.91) ==
* Tagging and branching (calligra/2.5) June 15th (no big merge on that day)
* Tagging and branching (calligra/2.5) June 15th (no big merge on that day)
* Release June 20th
* Release June 20th

Revision as of 12:12, 21 April 2012

Freezes

Master is never frozen for features or strings. The branch calligra/2.5 is always frozen for features or strings.

Testing

Alpha (2.4.90)

  • Tagging May 25th (no big merge on that day)
  • Release May 30th

Beta (2.4.91)

  • Tagging and branching (calligra/2.5) June 15th (no big merge on that day)
  • Release June 20th

RC (2.3.92)

  • Tagging July 6th (no big merge on that day)
  • Release July 11th

Stable releases

The final release should happen within three weeks after the RC.