Calligra/Schedules/2.5/Release Plan: Difference between revisions
Line 11: | Line 11: | ||
* Release May 30th | * Release May 30th | ||
== Beta (2. | == Beta (2.4.91) == | ||
* Tagging and branching (calligra/2.5) June 15th (no big merge on that day) | * Tagging and branching (calligra/2.5) June 15th (no big merge on that day) | ||
* Release June 20th | * Release June 20th |
Revision as of 12:12, 21 April 2012
Freezes
Master is never frozen for features or strings. The branch calligra/2.5 is always frozen for features or strings.
Testing
Alpha (2.4.90)
- Tagging May 25th (no big merge on that day)
- Release May 30th
Beta (2.4.91)
- Tagging and branching (calligra/2.5) June 15th (no big merge on that day)
- Release June 20th
RC (2.3.92)
- Tagging July 6th (no big merge on that day)
- Release July 11th
Stable releases
The final release should happen within three weeks after the RC.